Milestones

  • Hybrid Planning Application

    October 2021

     

    -

     

    March 2022

    Hybrid planning application submitted October 21 and due to be determined at planning committee March 22
  • Detailed Planning Application

    February 2022

     

    -

     

    July 2022

    Phase 1 works (Kings St) detailed planning application to be submitted mid-Feb and will be determined at planning committee June or July 22
  • Detailed Planning Application Approved

    November 2022

     

    -

     

    Spring 2023

    Bruntwood and Trafford Council have been given the green light to commence the ambitious transformation of Stretford’s King Street - the first phase of the wider Stretford Masterplan. The planning application was submitted in March 2022, following an extensive period of consultation with the local community to understand how the proposed development could reshape the future town centre to best serve its residents.
  • Development Begins

    June 2023

     

    -

     

    2024

    Work began on-site in June 2023, starting on the redevelopment of King Street to revive the area to the open-air high street of the past.
  • Public consultation

    06/10/2023

     

    -

     

    15/10/2023

    We will shortly be consulting the public on the next stage of our plans for Stretford Town Centre.